91p国产高清在线_日韩少妇内射免费_真实男女XX00动态视频午夜_亚洲国产综合在线成人视费观看_欧美双飞两白嫩18p图片_日本一区二区三区极品红色视频_五月综合久久婷婷_4438ⅹ亚洲全国最大色丁香_成人不卡免费观看_欧美NV在线播放

Steel Plate and Rolled Steel Pretreating Line

2593ef665c86f2298edca15a1e4980dc_2ffa2029cf0c28e.jpeg
      Preservation lines are used for pre- and final coating for large steel sheets, tubes and round bars, angle bars T beams C beams L beams and I-beams.
        The main area of application is coating parts with a welding primer for temporary corrosion protection. A preservation line usually consists of specially engineered conveyor systems,a pre-heater, a roller conveyor shot blast machine, an automatic paint spray system and a subsequent dryer. Depending on the customer requirements, different types of conveyor systems may be used, such as roller conveyors, chain or slat conveyors, crossconveyors,etc. The entire line is totally engineered around the specific application and size and geometry of the parts.
        The pre-heater, in connection with a blow-off unit,allows the processing of parts which are stored outside and may be covered with moisture or even snow or ice. Pre-heating the parts prevents moisture from contaminating the steel media and it reduces the drying time after coating the parts with a primer. The primer, which is sprayed onto the parts by the fully automatic painting system, is dried in a dryer located behind the painting system. Therefore, the treated parts are immediately available for the next manufacturing step without any delay.
        Shot blast systems
        The roller conveyor shot blast systems are an essential part of the overall preservation line. The parts (large steel sheets, tubes and round bars, angle bars and I-beams) travel on a roller conveyor through the pre-heater chamber,the blast chamber and a blow-off/brush-off station. The high performance blast wheels mounted to the machine housingensure all-round and reproducible blast coverage of the parts, while providing an optimal preparation of the parts surface for the subsequent primer coating and transport speed.
        1 Material
        Whether covered with rust or scale, whether processing sheet metal, profiles, tubes or welding constructions, whether large or small.
        2 Transport Systems
e.g. roller conveyors, chain (slat) conveyors, conveyors for the painting section, cross conveyors (lift and go), fork conveyors, shuttle conveyors,drives and controls for automatic conveyor lines, parts turning and collecting systems for welding constructions and tubes.
        3 Blow-off Station
        Blow off systems are utilized to remove moisture for example water puddles and loose debris from the material to be processed.
        4 Pre-Heater
        Heat is good against ice, cold and wetness. It prevents moisture from getting into the blast media. And it shortens the drying time after painting. The preheater brings the material up to painting temperature, thus facilitating the shot blast and paint process. Processing times are greatly reduced!
        5 Shotblasting Machines
        Rust and scale disappear in no time! The shot blast machine makes sure that the parts are cleaned to customer specifications.
        6 Patented Painting Lines
        Intelligent material scan systems minimize overspray. The special rotary brush pre-cleaner reduces the dust load in the dust collector by 60-80% Paint Supply e.g. airless or air atomizing systems,container or drum exhaust plants, paint heaters, mixing and distribution systems for 2K, solvent or water-based paints and coating materials, paint storage rooms according to WHG.
        7 Paint Dryer
        The drying takes place on a continuous basis in many variations:In front or behind the paint booth, heated by gas, oil or electric, with special overspray extraction zones and cooling zones. Floor suction systems and moveable dryers. The length of the dryer depends on type of paint, thickness of the paint layer
        8 Paint Treatment
        This system contains the dry and the wet paint processing mode.  Upper air emissions after the processing, the density of the tritan organic solution reaches the national environmental protection emission standard.
        9 Electric System
        The PLC programmable controller contains manual and automatic mode. This system is equipped with the central control room, the electrically control cabinet, the control table, branch control table and the branch control box, the control bench is equipped with the simulation screen to be possible to demonstrate the active status of the entire line.It is advantageous in observing and controlling the entire line and raises the working efficiency.
Blasting Line Model
Technical Coefficient

QXY2000

QXY2500

QXY3000

QXY4000

Parts of the Line

 Feeding

Swaying Feeding Rollgang

Swaying Feeding Rollgang

Swaying Feeding Rollgang

Swaying Feeding Rollgang

 Pre Heat

Lnfrared Heating

Lnfrared Heating

Lnfrared Heating

Lnfrared Heating

 Shot Blasting

XQ6920

XQ6925

XQ6930

XQ6940

 Painting

Working peed
0.5-1.2m/min

Working peed
0.8-1.5m/min

Working peed
0.8-1.5m/min

Working peed
0.8-1.5m/min

 Drying

Heated Air Circulation Heating

Heated Air Circulation Heating

Heated Air Circulation Heating

Heated Air Circulation Heating

 Paints Treatment

Dry-type Transiting Purify

Dry-type Transiting Purify

Dry-type Transiting Purify

Dry-type Transiting Purify

 Expulsion

Swaying Expulsion Rollgang

Swaying Expulsion Rollgang

Swaying Expulsion Rollgang

Swaying Expulsion Rollgang

 Electrical System

PLC CONTROL

PLC CONTROL

PLC CONTROL

PLC CONTROL

 Rust Removing Level

GB8923-88 A-BSs2.5

GB8923-88 A-BSs2.5

GB8923-88 A-BSs2.5

GB8923-88 A-BSs2.5

 Paint Firm Thickness um

15-30

15-25

15-25

15-25

 Total Power KW

415

480

510

530

 Total Wind Volume m3/h

22000

28000

38000

39000

The technical coefficients of the forms are only for indication.The details of the coefficient are subject to the technical projects.